Building Project

Kitchen & Dining Complex

Phase Two

We are nearing the end of our largest construction project to date.

To replace our 70-year-old Kitchen/Dining Room, we needed to divide constructing this new building into two phases. In September 2019, Phase One was completed and we moved in. Phase One's cost of $3.5 million was fully paid—and, because of our generous donors, we had enough to move seamlessly into Phase Two .

Work on Phase Two continued until we had to temporarily pause due to the uncertainty caused by the COVID-19 pandemic. Then after three months, we were ready to restart.

The building is on course to be finished by the fall of 2021. The cost of Phase Two is expected to be $1.9 million. We've raised more than half of that amount. With the help of many donors, we are well on our way to finishing this building that will be used as a tool for ministry.

To join us in making this a reality, consider giving a gift today.

 © Cannon Beach Conference Center 2020